The top global mining stories to the moment
Rolling 24/7 international mining news
POSEIDON NICKEL: RESOURCE UPDATE SUPPORTS BLACK SWAN PLANS
A 48% increase in measured and indicated contained nickel has strengthened the project operating model for Poseidon Nickel as it moves towards a final investment decision on the restart of mining at its Black Swan project in Western Australia.
The update by independent resource consultant WSP Australia on assay data to May 2023 delivers 118,000t (16Mt @ 0.73%) measured and indicated, within the total mineral resource of 189,000t (26.3Mt @ 0.72%). Both exclude 7,800t (1.6Mt @ 0.5%) in historical mine stockpiles.
MD-CEO Peter Harold says the upgrade is a key deliverable in Poseidon’s “fill the mill” strategy leveraging off Black Swan’s existing infrastructure including its 2.2Mtpa process plant.
POSEIDON NICKEL: RESOURCE UPDATE SUPPORTS BLACK SWAN PLANS
A 48% increase in measured and indicated contained nickel has strengthened the project operating model for Poseidon Nickel as it moves towards a final investment decision on the restart of mining at its Black Swan project in Western Australia.
The update by independent resource consultant WSP Australia on assay data to May 2023 delivers 118,000t (16Mt @ 0.73%) measured and indicated, within the total mineral resource of 189,000t (26.3Mt @ 0.72%). Both exclude 7,800t (1.6Mt @ 0.5%) in historical mine stockpiles.
MD-CEO Peter Harold says the upgrade is a key deliverable in Poseidon’s “fill the mill” strategy leveraging off Black Swan’s existing infrastructure including its 2.2Mtpa process plant.
GREEN TECHNOLOGY METALS: ONTARIO LITHIUM RESOURCE GROWS
Canadian-focused lithium explorer Green Technology Metals will assess the potential for stand-alone development of its 100%-owned Root project in Ontario after updating its inferred mineral resource to 12.6Mt @ 1.21% Li2O and 62ppm Ta2O5.
Root is 200km W of GT1’s flagship Seymour project, which holds indicated and inferred resources of 9.9Mt @ 1.04% Li2O and 137ppm Ta2O5.
CEO Luke Cox says the Root project update is just the beginning, with field exploration now started on an expanded untested area and the potential to host its own concentrator in line with its corporate strategy.
PERSEUS MINING: CREWS RETURN TO SUDAN PROJECT SITE
Miner/explorer Perseus Mining is preparing to return to its 70%-owned Meyas Sand gold project in Sudan, a little over a month after withdrawing most of its employees from the exploration project due to escalating armed conflict.
Perseus says the continuing conflict between rival military units has not resulted in any reported incidents near the project, which is nearly 900km N of Khartoum.
A security force led by company personnel and including national mining police as well as local community representatives will protect the site. Perseus expects to restart preliminary sitework and confirmatory drilling by end-June.
PEMBROKE RESOURCES: OLIVE DOWNS CELEBRATES MINING START
Developer Pembroke Resources has celebrated one of Australia’s largest steelmaking coal producers with the first dirt moving at its Olive Downs Complex in the Bowen Basin of central Qld.
Olive Downs is expected to reach its first shipments of high-quality coking coal and pulverised coal injection products in early 2024 to key markets including Japan, India and South Korea. Its JORC reserve of 527Mt is expected to sustain an 80-year mine life.
The official opening featured senior executives of full mining services contractor Thiess and equipment suppliers Caterpillar and Hastings Deering. The mine features the first autonomous-ready 794 AC haul trucks, CAT’s autonomous haulage system and autonomous drilling system in Australia.
MEGADO MINERALS: QUEBEC FIRES DELAY JAMES BAY LITHIUM SEARCH
International explorer Megado Minerals has halted plans to commence on-ground exploration activities at its Cyclone lithium project in the James Bay region of Quebec, Canada in mid-June due to the province’s wildfires crisis.
Quebec’s Ministry of Natural Resources and Forestry has banned access to forest lands and closed forest roads while crews battle to bring more than 160 fires under control.
With all geological exploration in the James Bay region banned, Megado and partner Dahrouge Geological Consulting have demobilised until further notice. CEO-MD Ben Pearson says it can’t avoid a delay but, as the companies were not yet fully mobilised, the impact should be minimal.
WESTGOLD RESOURCES: MUSGRAVE OFFER TARGETS CUE DEVELOPMENT
Australian miner Westgold Resources has gone public with a $A177M all-scrip off-market takeover offer for explorer Musgrave Minerals, a move it claims will provide a fast-track development route for Musgrave’s Cue gold project in WA.
It argues combining the companies will be safer than Musgrave’s proposal to develop a $121M stand-alone processing facility in a region already well serviced with processing infrastructure.
The 1-for-5.37 shares offer equates to 30cps, up from Musgrave’s 5-day VWAP of 22.9cps. Westgold made a confidential initial approach to the Musgrave board last week, but says a surge in share trading volumes shows the secret has been leaked.
BOWEN COKING COAL: $50M TO COUNTER ELLENSFIELD DELAYS
Australian miner Bowen Coking Coal has raised $A40M it hopes will help it counter third-party logistical delays that have slowed development of the Ellensfield South pit at its Burton Complex in Qld and impacted its near-term cashflow.
At the same time as completing its placement at 17ps with strong support from new and existing institutional investors, BCB has launched a $10M fully underwritten share purchase plan.
Ellensfield South is expected to deliver first coal in Sept, and at steady state its low-cost, high-yield output should substantially increase Burton coking coal exports.
KINCORA COPPER: ADVISER TO ASSESS GOBI PROJECT OPTIONS
Canadian-based explorer Kincora Copper has engaged international financial services company Cerberus Advisory to lead a review process after receiving unsolicited expressions of interest in its 100%-owned Southern Gobi copper-gold project portfolio in Mongolia.
Kincora says the review will consider partnering, funding and other asset initiatives for the assets, led by its Bronze Fox project with resources of 1.2Mt Cu and 0.8Moz Au.
Since conducting the first modern district-scale exploration across the region, Kincora has been seeking third-party investors while it turns its focus on its large Australian portfolio.
WINSOME RESOURCES: FIRE RISKS HALT FIELD EXPLORATION
The worsening risk of wildfires has led Winsome Resources to halt drilling and field activities at its projects in the James Bay region of Quebec, Canada.
With the province’s fire authority reporting it is battling 153 fires, Winsome says it has responded to its request to cease field exploration but will continue the processing of previously drilled core.
HILLGROVE RESOURCES: KANMANTOO MINE WORK STARTS AHEAD OF FID
A formal investment decision is imminent on Hillgrove Resources’ Kanmantoo copper-gold project in South Australia after gaining Foreign Investment Review Board approval for a $A17M placement by commodities trader Freepoint Metals & Concentrates.
Hillgrove says it has now raised a total $38M to complete underground development and continue mine life expansion drilling at its 100%-owned project 55km SE of Adelaide.
The company has already entered key contracts, appointed key employees and commenced underground development in anticipation of its final investment decision, remaining on track for first copper concentrate production in the March 2024 qtr.
BELLEVUE GOLD: PERMITS OPEN THE DOOR FOR MINE RESTART
The way is clear for Bellevue Gold to pour first gold in the Dec qtr from its 100%-owned namesake project in the West Australian Goldfields after gaining its state government tailings facility and water storage permits, the final approvals required for commissioning and full operation of the forecast 200,000ozpa producer.
Construction and underground development for the redevelopment of the historic project 40km NW of Leinster are running on time and on budget.
EVOLUTION MINING: STUDY EYES 17-YEAR LIFE AT ERNEST HENRY
Australian producer Evolution Mining has given the go-ahead for a full feasibility study into a underground expansion that promises to extend the life of its Ernest Henry mine by 11 years out to 2040 by delivering an extra 343,000t copper and 609,000oz gold.
The approval follows an update that more than doubled proved and probable reserves at the N Qld mine to 77.4Mt @ 0.76% for 589,000t Cu and 0.45g/t for 1.11Moz Au and a PFS that defined incremental NPV of $690-1,010M and IRR of 28-38%.
MD-CEO Lawrie Conway says, on top of the excellent PFS financial returns, Evolution’s current exploration success will further boost the new study.
ZIJIN MINING: ATTACKS FORCE MINING CUTBACKS
Attacks allegedly by illegal miners allied with a major crime gang have been blamed for the deaths of two workers and injuries to another 15 at a gold mine in Colombia owned and operated by Chinese government majority-owned Zijin Mining.
Zijin has shut down operations in 60% of the underground complex due to the risk of attacks by illegal miners, Reuters reports.
The attacks have become so frequent the Colombian Mining Association has suggested Zijin employees wear body armour and have police protection against gun attacks and attacks using cylinders of propane gas.
ENERGY TRANSITION MATERIALS: KVANFEJELD LETTER A PRELUDE TO ARBITRATION
It’s arbitration or nothing for Australian-based explorer Energy Transition Minerals after the Greenland government formally rejected its exploitation licence application for its 100%-owned Kvanefjeld project.
The project has been in peril since late 2021 due to the government’s opposition to uranium mining, given its significant occurrence among the rare earths, zinc and fluorspar content.
MD Daniel Mamadou says the government’s decision relates to its original 2019 application, which included uranium production. An amended application in Dec 2022 treating uranium as an impurity will be decided separately.
Mamadou says ETM has no choice but to continue with plans to lodge a statement of claim with Copenhagen’s arbitral tribunal in July.
PALADIN ENERGY: NAMIBIA DENIES ‘SEIZURE’ REPORTS
The Namibian government has moved to counter “misconceptions” that led to widespread reports it may seize minority stakes in mining and petroleum producers.
The fallout from media reports has impacted uranium miners and developers Paladin Energy, Deep Yellow, Bannerman Energy and Elevate.
“The government has no intention to seize any stake from existing mineral or petroleum licence holders and remain committed to uphold the sanctity of contract,” it said in a statement aimed at clarifying comments by mines minister Tom Alweendo last week.
It may demand a minimum stake through the state-owned Epangelo Mining or National Petroleum Corp in future mineral or petroleum licences to meet the Namibian people’s legitimate expectations of having an ownership share in the country’s natural resources.
EUROPEAN LITHIUM: SAUDI JV TO ADVANCE HYDROXIDE PLANT
Developer European Lithium has teamed with Riyadh-based investment giant Obeikan Group to jointly develop and operate a lithium hydroxide processing plant in Saudi Arabia with exclusive rights to process lithium spodumene concentrate from its Wolfsberg mining project in Austria.
Chairman Tony Sage forecasts the JV plant will strengthen the economics for Wolfsberg by significantly reducing Wolfsberg’s capital, energy and operating costs.
The JV, which will fully fund the plant development, will take up EUR’s binding lithium offtake agreement with premium carmaker BMW.
GHANA: SOLDIERS FIRE SHOTS AT MINING PROTESTERS
Ghanaian soldiers have fired shots to disperse protesters in the gold mining town of Obuasi in the Ashanti Region amid a crackdown on illegal miners, Al Jazeera reports.
The protest comes as hundreds of people remain underground after several days reportedly without food or water, either unable to exit or unwilling to leave for fear of being arrested.
Seven people who exited a shaft belonging to international miner AngloGold were arrested on May 30.
BEAR CREEK MINING: HEADWINDS THREAT TO Q2 MEXICAN MINE OUTPUT
Canadian-based Bear Creek Mining has warned that “significant headwinds” including inflation, exchange rates and below-target operating performance will impact the June qtr (Q2FY2023) results.
The warning by president-COO Eric Caba comes despite recent steps to improve production and decrease operating costs at its 100%-owned Mercedes mine in Sonora, Mexico and to improve its financial liquidity by restructuring certain debt and streaming obligations.
Caba says recent drilling results, dramatic changes in the operating cost structure and short-term funding restructuring support its confidence Mercedes will meet its FY2023 gold production guidance of 65,000-75,000oz at AISC of $C1,120-1,290/oz. March qtr production at Mercedes was 12,038oz gold and 40,241oz silver at $1,386/oz.
SHANTA GOLD: SINGIDA MOVES QUICKLY TO COMMERCIAL PRODUCTION
The rapid ramp-up in two months since its first gold pour has enabled East African miner Shanta Gold to declare commercial production effective June 1 at its Singida mine in Tanzania.
The company’s second Tanzanian mine reached its 1,000tpd nameplate capacity within weeks of its initial gold production on March 30 and achieved all key production measures including processing rate, plant availability, gold recovery and plant utilisation.
Mining activities at the Gold Tree openpit have built a stockpile of 187,673t @ 2.17g/t for 13,085oz, equating to six months of plant feed and including 37,844t @ 2.4g/t for 2,917oz in-plant crushed ore.
AUKING MINING: STUDY POINTS TO KOONGIE PARK FID
Australian explorer AuKing Mining will push on to more advanced development studies on its Koongie Park copper-zinc project after a scoping study confirmed the potential for a financially robust, globally competitive operation at Halls Creek in WA.
The study estimated total production of 110,000t Cu, 38,000t Zn and 355,000oz Ag over 11 years from the development of four openpit and one underground mine with onsite 750,000tpa processing facility.
It calculates preproduction capex of $A134M resulting in pre-tax NPV at 8% of $176.9M, IRR 39.7% and payback period of 2.45 years.
CEO Paul Williams says AuKing will progress technical and engineering workstreams leading to a final investment decision possibly late 2024.